Most of the deck support structure is in.  The framers started initial work on the roof of the outdoor room but then ran into a ‘big problem’.  This is BP #3.

  • BP #3:  Existing part of the roof on the back is not what was on the plans.  So, the design of the new roof has to be modified to match.  Meaning – we will have a different look as to how some of the roofs come together than what we thought.  Should not be a big deal.

Framers had two days w/no rain so they made good progress – but it is raining today.  The guys are showing up today who drive the piles to support the foundation.   We will likely have forms going up this weekend.



Leave a Reply

Fill in your details below or click an icon to log in: Logo

You are commenting using your account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s